SW update start date: 9/17
Schedule: Day 1 - 10K, Day 2 - soak, Day 3 - hold due to weekend, Day 4 - 100K, Day 5 - 400-500K (remaining)
So by the schedule above, all Ally’s should receive updates by next Friday.